Buildings and Grounds Committee
|
||||
|
Larry Bargy |
Michael Crawford, Chairman |
Eugene Dawson |
||
|
|
||||
|
SPECIAL MEETING |
||||
|
June 14, 2005 |
||||
|
Minutes |
||||
|
|
||||
|
Members present: |
|
Gene Dawson, Larry Bargy and Mike Crawford |
||
|
Members absent: |
|
None |
||
|
Others present: |
|
Pete Garwood, Jack White, Laura Sexton, Dave Vitale, Lou Basso and Dan Bean |
||
|
|
||||
|
1. Meeting called to order at 9:00 a.m. |
||||
|
2. Public Comment |
|||||
|
None. |
|||||
|
|
|||||
|
3. Jail Generator |
|||||
|
Chris Dewey, Fire Chief, joined the meeting. Mr. Dewey gave an account of the problem in the jail last weekend. The power was out on Friday for a number of hours. The generator in the jail picked up the lights but does not power the air handling system. The temperature in the jail was above 100 degrees. |
|||||
|
|
|||||
|
Discussion took place regarding whether to install a temporary generator vs. installing a permanent unit. |
|||||
|
|
|||||
|
Ms. Sexton indicated the dollars are available in the capital outlay fund to replace the current generator. |
|||||
|
|
|||||
|
Peter Garwood, Coordinator/Planner, indicated that the two choices are simply contracting with a generator supplier to install a generator on an emergency basis or having an electrical engineer draft specifications and go through the bid policy. |
|||||
|
|
|||||
|
The Committee had a speakerphone call with Jason VanBrocklin from Nealis Engineering. |
|||||
|
|
|||||
|
Motion by Larry Bargy, supported by Gene Dawson, to select D and R Electric as the contractor and Bridgeway Generator as the generator supplier, and get a diesel generator installed on an emergency basis. Motion carried – unanimous. |
|||||
|
|
|||||
|
Meeting adjourned at 9:55 a.m. |
|||||