2. Maintenance Department Update – Dave
Vitale |
|||||
|
|
·
Dave Vitale, Maintenance Director informed the Committee he intends
to send his employees to a workshop for cleaning training. |
||||
|
|
Dan Bean, Undersheriff joined the
meeting at |
||||
|
|
·
A dead birch tree on the north side of the |
||||
|
|
·
Lawn has been reseeded in the areas damaged by plowing and salt. Air compressor has been totally repaired
and is running very well. The public restrooms
are being closed one at a time for an intensive cleaning. |
||||
|
|
·
Courthouse Doors The door
closers on the North side of the 1905 Courthouse need to be replaced. Mr. Vitale presented a price for the
materials without installation, $1,159.89.
Mr. Vitale will check into the cost of installation by the same
company that supplies the closers. |
||||
|
|
Motion by Gene Dawson, supported
by Larry Bargy to recommend the Board of Commissioners approve the quote
(attached) from Twin Bay Glass for the materials and installation of door
closers at the 1905 Courthouse (north entrance) $1,489.89. Motion carried – unanimous. |
||||
|
|
·
Maintenance Department Work Orders Mr.
Vitale presented a draft of a Maintenance Request/Work Order Authorization
form to the Committee. |
||||
|
|
Motion by Larry Bargy, supported
by Gene Dawson to adopt the draft form of the Maintenance Request/Work Order
Authorization and direct Mr. Vitale to use the forms for departments to
request maintenance work in their area (attached). Motion carried – unanimous. |
||||
|
|
Mr.
Vitale will have some discretion whether to use the forms depending on the
magnitude of the job (e.g. not necessary for a light bulb change). |
||||
|
|
·
Jail Generator The
Committee reviewed a faxed copy of a quotation for a generator that would
power the jail in the case of a power outage.
The Committee had a speakerphone conversation with Mr. Bruce Otte with
Cummins Bridgeway, LLC regarding what the quote of $27,751.00 covered in
addition to the generator. Items not
covered are: installation, cabling, natural gas conversion, and a concrete
pad. No action taken at this time. |
||||
|
|
Mr. Vitale left the meeting. |
||||
|
|
Theresa Kent, Abstractor and
Sherry Comben, Treasurer joined the meeting. |
||||
|
3. Animal Shelter Update |
|||||
|
|
Bob
Yvon, Architecht and Pat Weisler, Contractor came in to update the Committee
on the Animal Shelter Construction. During
the initial excavation it was discovered water was close to the surface. A change order for tiling was initiated for
$4,000 to take care of the water problem.
Mr. Yvon noticed a culvert was not installed when the road into the
shelter was put in. Mr. Weisler will
check with the excavator. It was the consensus of the
Committee to send the change order to the Board of Commissioners for after
the fact approval (see attached). Mr. Yvon
proposed that for small changes, instead of initiating a change order for
each, presenting a change order for all changes at the monthly Committee
meeting. The Committee thought this
would work out well but indicated large change orders should be handled one
at a time. Mr. Yvon
presented a sample of the brick that could be used on the facility. Mr. Yvon
presented minor interior wall changes that were discussed at the last meeting
with him. The changes included an
animal bathing area, larger drop off area, an area for a washer and dryer,
and a larger quarantine area. Mr.
Weisler will get back to the Coordinator/Planner Office if there is any price
difference. Mr. Weisler
presented a sub-contractor list, and a timeline for completion. Mr. Weisler also indicated that the road
will be in by Monday and the construction will start shortly thereafter. |
||||
|
|
Undersheriff Bean left the
meeting. |
||||
|
4. Circuit
Court Jury Chairs |
|||||
|
|
The
Committee reviewed a communication from a recent juror (attached) that expressed
complaints about the Circuit Court jury chairs being uncomfortable. Peter Garwood, Coordinator/ Planner and
Laurie Sexton, Clerk will check into alternatives for the jury chairs. |
||||
|
5. 1905
Courthouse Roof |
|||||
|
|
Mike
Crawford and Arlen Turner will inspect the roof and report back at the next
meeting. |
||||
|
6. Office Space – Estimates |
|
|
|
Mr.
Garwood indicated he did not have the specifications ready for obtaining
quotes. Patty Niepoth, Register of
Deeds inquired about the timeline for the changes on the first floor so she
can plan for running the cable for a new computer network. The Committee recommended Ms. Niepoth have
the cable run, temporarily, from computer to computer without going through
the ceiling. |
|
|
Ms. Niepoth, Ms. Kent and Ms.
Comben left the meeting. |
|
7. Wheel Chairs |
|
|
|
Motion by Gene Dawson, supported
by Larry Bargy to recommend the Board of Commissioners purchase two wheel
chairs; one for the County Building and one for the 1905 Courthouse at a
price of $526.04 each ($1,052.08 total cost).
(see attached) Motion carried –
unanimous. |
|