Public Works Committee
Larry Bargy Joseph Allen, Chairman Eugene Dawson |
||
|
|
||
|
Minutes |
||
|
|
||
|
April 2, 2008 |
||
|
|
||
|
Members present: |
|
Larry Bargy, Gene Dawson and Joe Allen |
|
Members absent: |
|
none |
|
Others present: |
|
Pete Garwood and Jack White |
|
|
||
|
1. Meeting called to order at 9:00 a.m.
|
||
|
2. Public Comment |
|||
|
None. |
|||
|
|
|||
|
3. Building Department Update |
|||
|
Bob Massey, Building Official joined the meeting. Mr. Massey gave a verbal and written monthly report to the Committee. |
|||
|
|
|||
|
4. Drain Commission |
|||
|
Mark Stone, Drain Commissioner joined the meeting. Mr. Stone informed the Committee of a communication received by the Bill Stockhausen from the DNR regarding operation of the hydro facility. |
|||
|
|
|||
|
Mr. Stone and the Committee discussed the make up of an ad-hoc committee to address a report for the hydro facility that could be used for the FERC relicensing process. |
|||
|
|
|||
|
Mr. Stone updated the Committee on the status of outfitting the Bellaire Dam for operation by a generator in case of emergencies. |
|||
|
|
|||
|
5. Building Department - Revisited |
|||
|
Motion by Joe Allen, supported by Gene Dawson, to reduce the fee for bringing an issue before the Construction Appeals Board to $200, and if the Construction Appeals Board finds in favor of the contractor or homeowner the $200 will be refunded. Motion Carried – Unanimous. |
|||
|
|
|||
|
|
|||
|
The meeting was adjourned at 11:35 a.m. |
|||